Work Plan for the week of September 24, 2018

The following is to provide you with information of what you can expect on Lincoln Street in Biddeford for the upcoming week. Please note that this information is based on a projected schedule and is subject to change due to weather, work progress and/or other circumstances.

ALL BUSINESSES WILL REMAIN OPEN. PARKING FOR MULLIGAN'S PATRONS WILL BE IN THE LOT ACROSS THE STREET FROM THE RESTAURANT

Work includes the continued installation of underground conduit and vaults for the future underground placement of the overhead utility lines. Storm drainage structures will be installed.

Future Work

In the next several weeks the old road pavement and old gravel material will be removed, new road gravel installed, and base pavement installed. This work will be followed by installation of curbing and sidewalk placement.

Traffic Patterns

Traffic will continue to be one way from Main Street to Elm Street. Please follow detour and directional signage.